Dave Johnston Plant

On April 8, 2008, PacifiCorp, dba Rocky Mountain Power, filed an Application for a Permit Waiver to install new air pollution control equipment on Units 3 and 4 of the Dave Johnston electricity generating facility near Glenrock.  The retrofits will reduce emissions of sulfur dioxide and particulate matter in order to meet the State of Wyoming's requirements for best available retrofit technology controls.  The peak workforce for the retrofits is estimated to be approximately 450 with a projected increase of up to 12 additional Dave Johnston facility employees after the project is completed.  Construction would begin in the year 2008 and continue through 2010.  The facility is in operation.  08-01