On June 4, 2003, Uinta County Windfarm, LLC filed an Application for a Permit Waiver to construct an electrical generation facility with the Industrial Siting Division of the Department of Environmental Quality.  The facility is located in Uinta County north of Evanston.  The application stated that the project would be capable of generating 144MW of electrical power.  Construction would begin and end in the year 2003.   The application stated that construction workforce will employ an estimated average of 175 workers and the operations workforce will employ 10-14 estimated workers.  The construction cost was estimated to be $140M exclusive of interest.  The facility is in operation.  03-01