OnMay 24, 2005, Black Hills Corporation filed an Application for a Permit Waiver to construct an electrical generation facility, WyGen II.  The facility is located in Campbell County east of Gillette.  The project would be capable of generating 90 MW of electrical power.  Construction began in the year 2005 and ended in the year 2007.   The construction workforce proposed to employ a maximum of 400 workers per month and the operations workforce would employ 20 estimated workers.  The construction cost was estimated to be $148 million exclusive of interest.  The facility is in operation. Not all the files for this project are in a digital fomat.  If you would like to view the physical files, please contact the Division.  04-01